What is a change order in construction?

Study for the NCCER Module 00100 Construction Test. Use flashcards and multiple choice questions with detailed explanations. Prepare thoroughly for your construction career!

A change order in construction is a crucial document that modifies the original construction contract between the parties involved, such as the contractor and the client. This document is necessary when there are changes to the scope of work, schedule, or costs during the course of a construction project. It formally acknowledges and authorizes these modifications, ensuring that all parties are on the same page regarding the adjustments.

For example, if the client wants to add additional features or if unforeseen circumstances arise that require modifications, a change order is used to capture these changes legally and officially. This helps in maintaining clear communication and accountability among all stakeholders, preventing disputes or misunderstandings later on in the project.

The other options refer to different functions in construction management. Safety compliance pertains to the adherence to safety regulations rather than changes to a contract. A report of daily work activities involves tracking the progress and tasks completed without altering the terms of the contract. A checklist for project completion is used to ensure that all tasks have been finalized, but it does not involve modifications to the agreement itself.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy